Honduras: Reform of electricity sector, including tax incentive changes

Decree No. 198-2026 (Energy Justice Law)

October 7, 2026

Decree No. 198-2026 (Energy Justice Law), which was published in the Official Gazette on September 29, 2026, implements a comprehensive reform of the Honduran electricity sector, including regulatory, institutional, and tax changes with potential impacts on companies, investors, and consumers.

Main benefits and tax incentives

  • Exemption from income tax (impuesto sobre la renta, or ISR): New companies arising from the spin-off of the government-owned electric power company (Empresa Nacional de Energía Eléctrica, or ENEE) will be exempt from income tax for 10 years on generation, transmisión, distribution, and electricity marketing.
  • Tax exemption for residential solar: Residential solar systems (including solar panels, investors, batteries, and associated teams) will be exempt from sales tax (impuesto sobre ventas, or ISV), customs duties, and other taxes applicable to their importation or acquisition.
  • Residential electricity debt forgiveness: A forgiveness regime is approved for residential users with average consumption of up to 250 kWh per month (including capital, interest, surcharges, and accrued fines).
  • Regularization of illegal connections: An extraordinary period of three months is established for the voluntary regularization of irregular electricity supplies before the application of administrative and criminal measures.

Relevant institutional changes

  • Restructuring of ENEE: The law mandates the transformation and spin-off of ENEE into independent companies of generation, transmission, and distribution, as well as a new system and market operator (OSM). The OSM is created as an independent entity in charge of the technical operation of the national electricity system and the administration of the electricity market.
  • Strengthening the CREE: The Electric Energy Regulatory Commission (CREE) obtains greater financial independence, strengthened regulatory powers, and additional transparency obligations.
  • Renewable energy and storage: The law formally incorporates energy storage systems (batteries), hybrid power plants, storage's share of the electricity market, and regulations for users with grid-connected renewable systems. Likewise, the right of users to generate energy through solar systems and sell surpluses in accordance with the regulation issued by the CREE is expressly recognized.

Relevant dates and deadlines

Event

Term

Rate freeze

Six months extendable for six more months

Initial appointment of the OSM board of directors

60 business days

Start of OSM operations

140 business days

OSM rules of procedure

50 working days after the meeting is constituted

Reform Committee regulations

45 business days

ENEE subsidiary bylaws

120 days

Regulations for CREE appointments

120 days

Illegal connections regularization program

Three months

Mandatory public tender for energy

Start in 180 days

Conclude tenders

Maximum one year

ENEE historical debt report

120 days

FPS-ENEE actuarial report

12 months

Exemption from ISR for ENEE subsidiaries

10 years

Initial ENEE generation-distribution contracts

Up to 10 years

 

For more information, contact a KPMG tax professional in Honduras:

Luis Zelaya | lzelaya@kpmg.com

Thank you!

Thank you for contacting KPMG. We will respond to you as soon as possible.

Contact KPMG

Use this form to submit general inquiries to KPMG. We will respond to you as soon as possible.
All fields with an asterisk (*) are required.

Job seekers

Visit our careers section or search our jobs database.

Submit RFP

Use the RFP submission form to detail the services KPMG can help assist you with.

Office locations

International hotline

You can confidentially report concerns to the KPMG International hotline

Press contacts

Do you need to speak with our Press Office? Here's how to get in touch.

Headline