¹It should be noted that the Act is used in this article to mean the Procurement Act 2023 as well as associated legislation that support implementation of the Act such as the Procurement Regulations 2024.
²It should be noted that this article most of the examples used focus on the NEC4 ECC specifically however may be applicable to other contracts within the NEC suite of contracts, depending on the form of contract. ‘Contractor’ is the NEC term used for the supplier under the NEC4 ECC and the Contracting Authority would be the ‘Client’.
³Note that this section sets out a summary of the general obligations in the the Act in relation to performance and other reporting requirements. Note that within the the Act there are exemptions to the general obligations and Contracting Authorities should make sure they check these and whether they are applicable.
⁴Section 52 of the Act. It should be noted this is subject to the exceptions in relation to certain types of contracts and where the Contracting Authorities considers that the supplier’s performance under the contract could not appropriately be assessed by reference to KPIs.
⁵Regulation 32(2)(r) of the Procurement Regulations 2024.
⁶Section 71 of the Act and Regulation 39 of the Procurement Regulations 2024.
⁷Section 71 of the Act and Regulation 39 of the Procurement Regulations 2024. Contracting Authorities should note that this provision was effective from 1st January 2026 (noting that not all provisions within the Act where effective from the ‘go live date’).
⁸Schedule 7, paragraphs 12(3) and 12(4) of the the Act
⁹‘Excluded’ referring to an instance where a mandatory ground for exclusion applies and ‘excludable’ where a discretionary ground for exclusion applies.
¹⁰NEC also provides for KPIs in other contracts, for example the FAC-1 Framework Alliance Contract.
¹¹For example, in the NEC User Guide ‘Preparing an Engineering and Construction Contract’.
¹²Regulation 39(5) of the Procurement Regulations 2024 prescribes that the rating system for KPIs is to be based on a scale of: Good – Performance is meeting or exceeding the KPI, Approaching Target – Performance is close to meeting the KPI, Requires Improvement – Performance is below the KPI, Inadequate – Performance is significantly below the KPI. Other – Performance cannot be described as good, approaching target, requires improvement or inadequate.
¹³See example boilerplate clauses for use with the NEC4 ECC - Construction Works and Associated Services 2 (CWAS2) / ProCure 23 (P23) - CCS.
¹⁴Section 70 of the Act. Contracting Authorities should note that this provision was effective from 1st April 2026 (noting that not all provisions within the Act where effective from the ‘go live date’).
¹⁵For example, S 800 in the NEC4 ECC or S 500 in the NEC4 Professional Services Contract (PSC) if using the standard scope sections.
¹⁶Note that this section sets out a summary of some of the obligations in the Act in relation to implied terms. Note that within the Act there are exemptions to the general obligations and Contracting Authorities should make sure they check these and whether they are applicable.
¹⁷Public Contract Regulations 2015; Regulation 113(2)(a) and Regulation 113(6)(a).
¹⁸The ‘Electronic Invoicing and Payment’ Guidance published by the Government in February 2026 confirmed this to be the case and that there is an intention to clarify the wording of section 68(2)
¹⁹Section 68 of the Act.
²⁰Section 68(6) of the Act.
²¹Section 73 of the Act.
²²Section 78(2) of the Act.
²³Section 80 of the Act.
²⁴Note that invoices though are a feature of other NEC4 contracts such as the Professional Services Contract (PSC) and Facilities Management Contract (FMC).
Procurement Regulations 2024
²⁵Note that this section sets out a summary of some of the obligations in the Act in relation to contract modifications. Note that within the Act there are exemptions to the general obligations and Contracting Authorities should make sure they check these and whether they are applicable.
²⁶Section 74 and Schedule 8 of the Act.
²⁷Regulation 40 of the Procurement Regulations 2024 and Section 77 of the Act.
²⁸Section 75 of the Act.
²⁹Section 77 of the Act.