The GTF inspection process will include a heavy workscope replacing life limited parts, which extends the shop time. P&W is predicting between 250 and 300 day turnaround time per engine but there are some that put a question mark around that estimate.
Aircraft and engine lessors are witnessing the impact first had. The engine leasing sector is divided into long-term spare engine leases – around 10-12 year leases – or shorter term lease used to cover short-term requirements such as MRO shop visits. Currently, we’re seeing a significant shift in demand patterns due to the labour shortage in the MRO sector and a scarcity of parts, which has led to extended shop visit durations.
“Previously, a full refurbishment might take between 90 to 120 days, but now we’re looking at more than 180 days,” says Bobby Janagan, managing director of Rolls- Royce Partners Finance (RRPF). “This change has naturally increased the demand for short-term engine leases, with customers now seeking spare engines for longer durations to accommodate these extended MRO turnaround times. The MRO shops are filled with engines awaiting parts, effectively blocking capacity. The MRO and supply chain are diligently working to optimise capacity and source parts as quickly as possible, and increasingly target used parts, yet the demand for parts continues to outpace supply.”
Greg Conlon, chief executive of High Ridge Aviation, said that finding engine MRO slot availability was difficult and taking much longer to complete. “Typically pre-Covid, it took 45 days to get any engine through a shop visit prior to the GTF issues. Now we are getting quotes from 210 to 270 days to shop an engine.”
RTX said in October that it has made progress with increasing MRO capacity by accelerating investments in its GTF network, with capacity added to Singapore facility and Iberia Maintenance joining the aftermarket network at the end of 2023. The network at full force will have 16 sites around the world, with plans for a further three shops to come online by 2025. P&W says it will be able to conduct more than 2,000 annual shop visits in 2025 – a fivefold increase over 2019.
MRO capacity is at a premium but industry experts are agreed that the lack of parts and constraints in parts production is a significant variable in P&W’s published fleet management plan.
“Parts are a big problem for Pratt,” says one expert. “Those parts cannot be repaired so need to be produced. Pratt will need to double the production of its discs and they are already behind in ramping up after the pandemic.”
Not every part in the affected engines will be rejected – maybe one part for every ten inspections, says one lessor, who adds that to put in place the extra production and MRO capacity, the industry will need to “work harder and faster, smarter to get this done quickly because the MRO capacity is pretty tight”.
RTX has promised to replace as many HPT and HPC discs as possible with full life discs during shop visits to maximise time on wing. There have been doubts around whether the company can produce the increase quantities of discs in a shortened timeframe but Calio said in October that the company was accelerating its baseline forecast for run rate capacity disc production.
RTX chief executive Gregory Hayes said in October that he believes the company has its “arms around the operational and financial impacts of the powdered metal issue” and is now focused on executing those fleet management plans.
Regarding the recent challenges with new equipment, RRPF’s Janagan notes: “Issues at Entry into Service (EIS) with new equipment are somewhat anticipated in our industry,” he says.
“However, the magnitude of the GTF issue is really unfortunate for our airline customers. That said, Pratt & Whitney has identified a solution and is working in close collaboration with customers to rectify the situation. To Pratt’s credit, they have been very cooperative, providing essential information to all key stakeholders. However, the plan to rectify the situation, while necessary, will inevitably lead to further supply constraints. As a result, we’re seeing strong demand for previous generation engines and an extension in the useful lives of older engines as the market adapts.”
RRPF’s Janagan expects the OEMs and MRO shops to work through the parts shortage by late 2024 and into 2025 as the manufacturing sector resolves shortages of resources and supply.