1) Understanding the Fault Ride Through issue and proposed solutions
Impacted parties: Data centres connected to the transmission system.
Summary: In November, EirGrid published a Grid Code modification proposal in response to growing concerns that the scale of data centre electricity demand could pose significant risks to the stability of Ireland’s grid. The matter is technical and centres on a grid operations issue known as transient faults.
The concern is that, following a temporary disturbance on the grid, one or more data centres will disconnect from the grid and rely upon their onsite power solutions. This could create additional disturbances, triggering further data centres disconnections.
Such an event could lead to a sudden, large imbalance between supply and demand on the grid, leading to large changes in grid frequency. EirGrid has estimated that imbalances could reach over 1,150 MW if no additional mitigating action is taken.
Similar risks were identified and addressed when Ireland began connecting large renewable generators to the grid. The wind generator technology at the time meant the generators would disconnect from the grid if they sensed a frequency disturbance, which could have led to too little generation serving demand from the grid leading to grid frequency drops.
The proposed solution in both instances, at a high-level, entail modifying the Grid Code so that large facilities must in the first instance be more tolerant of disturbances and also reconnect to the grid within a specified timeframe.
Specifically, the proposed modifications would require data centres to:
- Remain connected during a Rate of Change of Transmission System Frequency (RoCoF) of up to and including 1 Hz per second, measured over a rolling 500 milli-second period;
- Remain connected during and following power system fault disturbances which result in a voltage deviation which remains on or above the profile detailed in Figure 4; and
- Return to at least 90% of pre-fault demand within 500 milliseconds of the transmission system voltage recovering to 90% of the nominal voltage, with the required ramp up rate to be agreed between the TSO and the data centre owner.
EirGrid continues to engage and collaborate with industry on these proposed solutions. Industry keenly awaits the final agreement of solutions, which will impact all current and future data centres in Ireland.