Reference designs for data centres remained stable for a significant period. By adopting uniform designs across multiple projects, large data centre developers (such as hyperscalers and larger colocation providers) reduced procurement complexity, facilitated easier maintenance, and improved scalability.
However, the design of data centres has recently become volatile. Existing reference designs are no longer adequate and need to be replaced. The industry is at an inflection point with AI on the cusp of significant growth. To future-proof data centres, operators now need to plan for racks in the 100-200kW range.
Designers face the challenge of developing flexible plans that allow air and liquid cooling solutions to coexist, potentially transitioning to more sophisticated liquid cooling approaches as cooling technology evolves and immersion cooling becomes more commercially viable over time.
This includes incorporating provisional space for new items of owner furnished equipment such as Coolant Distribution Units (CDUs), thermal storage buffer tanks (to allow for the accumulation of sufficient chilled water during a chiller restart as a result of a power loss) and additional mechanical Uninterruptible Power Supply systems (UPSs) and batteries to support the CDUs or mechanical UPSs to support the Chillers.
Commissioning of liquid-to-liquid data modules adds a further level of complexity to an already onerous process so commissioning plans must include these detailed requirements from day one and be integrated into purchase requirements and tender documents at the earliest opportunity to mitigate supply chain challenges.